• July 2021 – Land acquisition
  • July 2021 – Zoning/ordinance changes approved by the City of Milford
  • September 2021 – Architect selection through RFP process (Becker Morgan)
  • October 2021 – Construction management selection through RFP process (Whiting Turner)
  • November 2021 – Preliminary construction design begins
  • August 2022 – Sediment and erosion control begins
  • September 2022 – Official groundbreaking
  • December 2023 – Anticipated construction completion and receipt of certificate of occupancy